When treated pine suits
Treated pine (softwood treated with preservative) is the lowest-cost way to get a timber deck. It suits:
- rentals and first homes where budget comes first;
- decks you plan to paint or stain a colour rather than oil;
- low platforms, landings and step-downs;
- framing under any deck, including hardwood and composite ones.
It needs a coating to stay in good shape in Wagga's sun. If you are deciding between the two, see treated pine vs hardwood decking or our hardwood decks page.
Hazard classes: what goes where
Pine is treated to a hazard class under AS 1604. The class decides where it can be used, and a deck uses more than one.
| Class | Exposure | Where it goes on a deck |
|---|---|---|
| H3 | Outside, above ground | Deck boards, joists, bearers and handrails above ground |
| H4 | In ground or continually damp, non-critical | Framing within 150 mm of the ground, landscaping |
| H5 | In ground, critical structural use | Posts set in the ground, stumps |
H1 and H2 are for inside use only and are not suitable for decks. H3 pine must never go in the ground. In-ground posts need H5, or in-ground Class 1 hardwood.
Every piece of treated timber must be branded with the treatment plant number, the preservative and the hazard class. Addan checks the brand on delivery, and you can check it too.
Treatment type near children
Most treated pine is CCA (copper chrome arsenate), ACQ, copper azole or LOSP treated. The rules differ:
- CCA-treated timber must not be used for deck boards or handrails where children may have frequent contact. It can still be used for subfloor framing.
- ACQ, copper azole and LOSP treatments can be used for decking and handrails.
So on a family deck, the boards and rails need a non-CCA treatment. If you are pulling up an old pine deck, CCA offcuts must never be burned. The smoke and ash contain high levels of arsenic. Existing CCA structures don't have to be removed.
How a pine deck is built
- Footings. Posts sit on galvanised stirrups in concrete footings, at least 75 mm above the ground for termite inspection. If a post goes into the ground, it is H5.
- Frame. Bearers and joists are sized from AS 1684 span tables or by an engineer, using the figures for the grade of pine being used.
- Joist spacing. No more than 400 mm apart for 19 mm treated pine boards, or 450 mm for 22 mm boards. About 350 mm if the boards are laid at 45 degrees.
- Boards. Gaps are set to suit the board and its moisture content, and the boards are kept 10 mm clear of the house wall.
- Fixings. Two fixings per board at each joist, at least 12 mm from the ends, in hot-dip galvanised or stainless steel. Electroplated screws are not used.
- Ventilation. Decks under 400 mm off the ground get wider gaps and airflow underneath.
Finish and upkeep
Bare pine greys, checks and splits in the sun. Wagga averages almost 32 °C in January and has around 21 frosts a year, which works the timber hard. A deck stain, oil or paint system protects the surface and lets you choose a colour. Recoat as the product's maker recommends, sooner on decks in full sun. Sweep or blow the deck clean rather than hosing it.
Once a year, push and pull on the balustrades and handrails, check fixings for rust and look for soft or spongy timber. The deck maintenance checklist lists what to look for.
Termites
Wagga is in a termite risk area. Whatever the timber, the deck must not bridge the house's termite management system, so it is kept at least 25 mm clear of the building or the barrier is extended.
Approval, licence and price
Material doesn't change the approval rules. A deck is exempt only if it meets every Codes SEPP standard, including the 1 m floor height and 25 m2 area. Otherwise Addan arranges a CDC or DA. On bush fire prone land, an exempt deck within 5 m of the house must be non-combustible, so a pine deck there needs approval. Addan holds an NSW Contractor Licence (Individual), class Carpenter, number 391427C.
Price depends on size, height, shape, stairs, balustrades, access, slope and the coating. Use the instant estimate for a range, or send an enquiry for a free on-site quote.
Common questions
Is treated pine good for decking?
Yes, if it is the right hazard class and treatment. Boards and above-ground framing need at least H3, in-ground posts need H5, and boards and rails near children should not be CCA treated. It needs a protective coating.
What H class do I need for a deck?
H3 for boards and above-ground framing, H4 for framing within 150 mm of the ground, and H5 for posts set in the ground. H2 is not suitable for decks.
Is CCA treated pine safe for a deck?
CCA must not be used for deck boards or handrails where children may have frequent contact. It is still allowed for subfloor framing. ACQ, copper azole and LOSP treatments can be used for boards and handrails.
Can I paint a treated pine deck?