Addan designs and builds decks from ground level to multi-level in hardwood, composite or treated pine. He measures up, quotes in writing and builds every job himself.

What we build

AJS Carpentry builds new decks around Wagga Wagga and Riverina towns within about 200 km. The range covers:

  • low decks off the back door, a step or two above the lawn;
  • raised decks on sloping blocks or at the height of a high-set floor;
  • multi-level decks that step down a slope or wrap around a corner of the house;
  • front decks and entry landings with steps;
  • freestanding decks out in the yard, by a pool or under a tree.

Every deck is designed around the block. Addan looks at where the sun sits in the afternoon, where water runs when it rains, where the doors open and how the deck will connect to the lawn, paths and any pergola you want now or later.

Materials

You choose the boards. The frame underneath is sized to suit them.

MaterialWhere it suits
MerbauImported hardwood with a red-brown colour and durable heartwood
Spotted Gum and BlackbuttAustralian hardwoods, lighter and more varied in colour
CompositeTrex, ModWood and Millboard boards. No oiling, follow the maker's care instructions
Treated pineThe budget option. Takes paint or stain

The best decking timber guide compares them.

How Addan builds a deck

  1. Measure-up and quote. Addan comes out, measures the site, checks the levels, the soil and access, and talks through layout and materials. You get a written quote, and what's quoted is what gets built.
  2. Approvals. If the deck needs a complying development certificate (CDC) or a development application (DA), Addan arranges it, along with an engineer where one is needed. He is not the certifier or the engineer.
  3. Set-out and services. The deck is pegged and string-lined. Underground services are located through Before You Dig Australia, which is free.
  4. Footings. Holes are dug and posts set on concrete footings with stirrups. Wagga's red clays are often moderately reactive, so footings go down to firm ground.
  5. Frame. Bearers and joists are sized from AS 1684 span tables, or to an engineer's design. Joist spacing suits the board: for 19 mm hardwood decking, no more than 500 mm.
  6. Boards and finish. Boards go down with even gaps and two fixings at every joist, using hot-dip galvanised or stainless steel. Timber decks are oiled or coated.
  7. Handover. A walk-through together, with care tips for the material you chose.

Most jobs take a few days to two weeks on site.

Termites and ventilation

Wagga is in a termite risk area. The NCC lists decks, verandahs and steps as attachments that must not bridge the house's termite management system. Where the house has a barrier, the deck is kept at least 25 mm clear of the building or the barrier is extended. Posts on stirrups are kept at least 75 mm above the ground for inspection, and the boards next to the house are screwed down so they can be lifted.

Decks under 400 mm off the ground need narrower boards, wider gaps and enough airflow and drainage underneath, or the frame stays damp.

Council approval

A deck can be exempt development, with no approval needed, only if it meets every standard in the Codes SEPP, including:

  • floor no more than 1 m above existing ground level;
  • area no more than 25 m2, and within 15% of the house's ground floor area for all such structures on a lot over 300 m2;
  • behind the building line, and at least 900 mm from each boundary (5 m in rural zones and R5);
  • no higher than 3 m overall;
  • not on a heritage item, and non-combustible within 5 m of the house on bush fire prone land.

If any one standard is missed, the deck needs a CDC or a DA. In Wagga the Inland Code sets the CDC rules, and DAs go through the NSW Planning Portal. An exempt deck still has to meet the Building Code. Addan checks all of this at the quote. More in the deck council approval guide.

Building rules

  • Licence. Residential building work over $5,000, including GST, needs a contractor licence. Addan holds an NSW Contractor Licence (Individual), class Carpenter, number 391427C.
  • Contracts. Jobs over $5,000 need a written contract. Jobs over $20,000 need a major work contract, a cooling-off period and Home Building Compensation Fund insurance. The deposit can't exceed 10%.
  • Balustrades. Where it is possible to fall 1 m or more, the NCC requires a barrier at least 1 m high. See deck stairs and balustrades.

What affects the price

Size, height off the ground, board material, shape and number of corners, slope and access, stairs, balustrades, removal of an old deck, and whether council approval or engineering is needed. For a price range in about a minute, use the instant estimate. The on-site quote is free.

Common questions

How much does a deck cost in Wagga?

It depends on size, height, material, stairs, balustrades and access. The instant estimate gives a range in about a minute, and Addan then measures up for a free written quote.

Do I need council approval for a deck?

Only if it misses any of the exempt development standards, such as the 1 m floor height, the 25 m2 area or the boundary setbacks. Heritage and bush fire prone land change the answer. Addan checks it at the quote and arranges approval when it's needed.

How long does it take to build a deck?

Most jobs take a few days to two weeks on site. Approval time, if needed, comes before that. You get a timeframe with your quote.

Which decking material lasts longest?

Durability depends on the material and the upkeep. Merbau, Spotted Gum and Blackbutt heartwood are all rated Class 1 above ground. Composite boards need no oiling. Treated pine needs to be at least H3 for boards.

Do you build decks outside Wagga?

Yes, in Riverina towns within about 200 km, such as Junee and Coolamon. Travel is included in the quote.